The history of “Highway 100” is a little confusing, because it can either mean:
- The Original Highway 100, which was built between 1934 and 1941 along 12.5 miles between Highway 5 (78th Street) in Edina and Highway 52 (now Highway 81) in Robbinsdale;
- The Present Highway 100, which runs from I-494 to I-694; or
- The “Belt Line,” which was a precursor to the present 494/694 circle around the Twin Cities. This Belt Line, of which the Original and Present Highways 100 were a part of, existed from 1950 to 1965
Thanks to Jeanne Andersen for this clarification.

1922 | Born and raised in Germany, Carl Graeser earned a civil engineering degree from Vermont’s Norwich University in 1909. He joined the Minnesota Highway Department (now MnDOT) as a project engineer in 1922. He became a champion for the Belt Line project.

April 5, 1928 | Highway Engineer Carl Graeser appeared before the St. Louis Park Village Council to obtain consent to the plans and specs for Highway 5 (100). It became a village in 1886.

1930 | It was to be built along 12.5 miles between Highway 5 (78th Street) in Edina and Highway 52 (now Highway 81) in Robbinsdale.
July 23, 1931 | State and county officials agreed on plans to construct the Belt Line road along western limits, which was authorized at the last session of the legislature. They approved an 11-mile stretch from Robbinsdale to Highway 52. (Highway 100’s route eventually spanned 12.5 miles to 78th Street in Edina.)

1932 | Arthur R. Nichols became the Roadside Development Division’s Consulting Landscape Architect, remaining until 1940. He designed and supervised the execution of Highway 100 and Lilac Way. Nichols was trained in engineering and highway design, as well as in landscape architecture.
April 18, 1932 | The land was previously farmland and personal residences. Many properties were purchased through eminent domain.

Early 1930s | (Need to confirm date) A son of an immigrant from Hanover, Germany, Dr. Fred C. Obermeyer’s family farm was one of many purchased for an easement to build the West Belt Line Highway in the 1930s. Their farm was sold so Highway 100’s Lilac Way could be built. The designer of the Belt Line was Carl Graeser, a German immigrant born in Windisch-Marchwitz, Schlesien, Germany. Photo: Beth Sartor Obermeyer.

March 4, 1933 | He declared a war against economic hardship as nation was reeling from the Great Depression. His New Deal program launched the Works Progress Administration (WPA) to provide employment. Highway 100’s Lilac Way was MN’s largest WPA project.

June, 1933 | A New Deal agency, the PWA was set up by Pres. Franklin D. Roosevelt to reduce unemployment through the construction of highways and public buildings. These projects created jobs and stimulates the economy during the Great Depression. Unskilled workers were required to be local. When possible, men, horses, and hand tools would be used instead of heavy machinery, to provide work.
Summer, 1933 | A survey of the route was done using two crews, one truck, and equipment left over from World War I.

1934 | Excavation for the first Highway 100 segment began in Edina. This leg of the new highway extended from West 50th Street/Vernon Avenue in Edina to Excelsior Boulevard in St. Louis Park.
1935 | Phase two began between Excelsior Boulevard and Wayzata Boulevard. Construction was speeded up from 20,000 yards per month to 120,000 yards per month.

1935 | The Federal Emergency Relief Administration (FERA) was a program established by President Franklin D. Roosevelt in 1933. It was replaced in 1935 by the Works Progress Administration (WPA).

April 3, 1935 | Land for the Belt Line highway around Minneapolis near Wayzata Boulevard was bought by the state highway department at 16 times its book value. The average price of $1,150 per acre was paid for 45.33 acres.

1935 | The first 3,500 of 7,000 lilacs were planted along two miles of highway between Glenwood Avenue and Medicine Lake Road in Golden Valley, MN.

July 9, 1935 | Highway 100 helped provide work for 3,500 homeless men. Each man worked six hours a day for six days and were limited to 40 hours per month. They earned 55 cents an hour or $19.80 in cash in lieu of the $10.80 they had received in meal and lodging tickets. The men had previously been transported in open dump trucks.

July 28, 1935 | Inspired by Washington, D.C.’s cherry blossoms, in 1935 the Minneapolis Journal proposed planting lilacs along the new Highway 100. More than 50,000 citizens in 40 civic and business groups supported the idea. The Minnesota Highway Department Department agreed, and Lilac Way’s story began. The headline proclaimed, “Highway Department Approves ‘Lilac Way’ West of City, Journal’s Plan for Beautifying Belt Line OK’d.”

1935 | After 4,500 men were given physical exams, 3,000 were qualified to work on the Highway 100 project. As the largest Federal work relief project in MN, the Belt Line’s construction provided an immediate boost to the economy. At the height of the Great Depression, nearly one in four Americans was unemployed. Photo by John Vachon.

August, 1935 | C.M. Stafford of the Saddle and Bridle Club urged the state to add a dirt or tanbark road for the purpose of driving horses: “hackneys with snappy carts,” then a popular occupation. He stated that there were more than 2,500 people who rode or drove horses in Minneapolis.

Two bridges spaced 10 ft. apart were under construction for the Milwaukee/St. Louis Railroad railroad overpass at Highway 7.

1937 | Approximately 1,500 men worked on the project every day. As the largest Federal work relief project in the state, the building of the Belt Line provided an immediate boost to the economy. Its biggest year was 1938. In Minnesota, 600,000 people had been employed by the WPA.

Late 1930s | The Garden Club sold French lilac bushes (15 cents) and peony roots door-to-door to pay for plantings along the local stretch of Highway 100. They raised enough money to purchase almost 7,000 lilacs to beautify the new Lilac Way, the showcase section of Highway 100.

1937 | Construction began on the northern section of Highway 100, from Glenwood Avenue to Highway 52 (now 81).

July, 1937 | The opening of (one section of) the new highway was celebrated with a picnic in Golden Valley. Thousands gathered for sports events, fireworks and a salute to city pioneers.

August, 1937 | The Minneapolis Journal reported that work would be accelerated so Highway 100 could be open between Excelsior Blvd. and Robbinsdale before winter. The state highway department said the project would be completed by 1938. Two bridges had yet to be built, although the cloverleaf at Wayzata Blvd. was underway. Only 400 men were at work on the project.

Grading of 3.7 miles between Wayzata Blvd. and Robbinsdale complete

November 26, 1937 | The Highway 100 / Highway 12 Cloverleaf was opened. Construction had started on June 20. The Hennepin County Review reported that the cloverleaf was the “Northwest’s first cloverleaf highway grade separation.”
December, 1937 | A cloverleaf was planned for Excelsior Boulevard. An article stated that the new Highway 7 was carrying the heaviest traffic load in the state, so plans for the second cloverleaf were changed from Excelsior Blvd. to Highway 7.
December, 1937 | The Minnesota Highway Department reported that Highway 100’s construction was 80% completed.

January, 1938 | The bridges at Highway 7 and Minnetonka Blvd. were the only things preventing the opening of the new highway. Fourteen bridges had already been built, including an ornamental concrete bridge over Minnehaha Creek in Edina, and the bridge that went over 44th Street and the streetcar tracks.

January 30, 1938 | Nels W. Elsberg, MN State Highway Commissioner (1933-38), stated that the new section of highway was not only safer than earlier roads in the state, but nothing less than “one of the most beautiful in the world” (Minneapolis Journal).
1939 | The Highway 7 and Minnetonka Boulevard overpasses were completed.

1939 | When the cloverleaf at Highway 7 opened, it required 30 acres of land and cost $65,000 ($1,500,000 in 2025 dollars).

September 1, 1939 | 3M’s Scotchlite Reflective Material was used on traffic control signage, and installed at the Highway 7 cloverleaf. 3M was founded in Minnesota in 1902.

1940 | Construction of Graeser Park, the largest of Lilac Way’s seven parks, was completed. It included a beehive fireplace, 18 stone picnic tables, and a rock garden.

January 10, 1941 | Highway 100 between Highway 5 (78th Street) in Edina and Highway 52 (now Highway 81) in Robbinsdale was completed. It included more than 7,000 bushes of 12 varieties of lilacs and thousands of other shrubs, vines, and trees. With the onset of World War II, workers and materials were diverted to the war effort.

March 15, 1944 | Known as the ‘Father of the Belt Line’, Carl F. Graeser, 70, was found dead at the wheel of his car. Lilac Way’s Graeser Park in Robbinsdale, MN, is his namesake.
1950 | The Highway Department combined new highways and existing roads to form a 66-mile radial route around Minneapolis/St. Paul. For 15 years, this entire Belt Line was also known as Highway 100. The road in South St. Paul was comprised mostly of industrial roads. The concept of the Belt Line was lost with the construction of 494/694 in 1965.

July, 1951 | On just one day, more than 20,000 vehicles were counted traveling down Highway 100 north of Excelsior Boulevard at a a 50 mph speed limit.

July 12, 1955 | Council approved state highway department’s 4-lane divided highway ‘Super’ Belt Line across 78th St., to be the first link in an 80-mile super-highway encircling the Twin Cities.

1959 | Glenwood Avenue Roadside Park was the first Lilac Way park to be lost to road construction. It featured picnic tables and a rectangular fireplace with two grilling areas in the NW corner of Highway 100 and Glenwood Avenue in Golden Valley, MN.
1965 | With the completion of 494/694 in 1965, the term “Highway 100” Belt Line was no longer in use. It is no longer possible to directly follow the path of the old Belt Line.

1969 | Located on the busiest and deadliest intersection in MN, Lilac Way’s Excelsior Boulevard Park on Highway 100 was razed for road construction. It featured a beehive fireplace, stone picnic tables, a stone signpost and a parking structure.

January 23, 1970 | Lilac Way’s landscape architect Arthur Nichols died in Rochester, MN at 89. He was a consultant for the MN Highway Department in the 1930s.

April 25, 2008 | Karen Laukkonen was stunned to see salvaged 1930s Lilac Way stone picnic table tops, bases and stone pieces stacked in a MnDOT parking lot. Known as the ‘Beehive Graveyard’, the stone was salvaged from three parks before they were razed for 2001 road construction. It included Graeser Park’s picnic tables, removed to create a construction staging area.

May 7, 2008 | Inspired by TPT’s ‘Highway 100: Lilac Way” film, Karen Laukkonen developed a campaign to restore 3,000 lilacs with community sponsorship, reduce strain on municipal and MnDOT budgets and revive pride in a historic area. The project has now changed to Restore Lilac Way to document history and support restoration.

October 22, 2008 | The city of St. Louis Park saved this rare 1930s beehive fireplace from demolition for road construction. It was carefully moved from Minnetonka Boulevard to another Lilac Way park near Highway 7, just one mile south.

July 13, 2009 | Lilac Park was beautifully revived by the city of St. Louis Park, MN. It includes a beehive rescued from demolition, five picnic tables and a council ring. It is located at Highway 100 and County Road 25/Highway 7, just west of Nordic Ware.

April 29, 2018 | Karen Laukkonen launched a completely rebuilt and redesigned restorelilacway.com site. First launched in 2008, it included mobile design, tons of new info and many historic documents and photos.

August 8, 2020 | Karen Laukkonen at Restore Lilac Way contacted Andrea Weber, Manager of MnDOT Historic Roadside Properties Program, to approve an Eagle Scout project in Rock Island Park. This innocent request changed Lilac Way’s history forever, leading Andrea to investigate Graeser Park and Rock Island Park. After seeing enthusiastic community support for both historic parks, she directed a three-year, $500,000 Graeser Park restoration and removed diseased trees and invasive species while preserving the intact original lilacs in Rock Island Park.

Spring, 2021 | Andrea S. Weber, Professional Landscape Architect and Program Manager of MnDot’s Historic Roadside Property Program, directed a series of restoration projects at Graeser Park totaling just under $500,000.

Spring, 2021 | MnDOT Historic Roadside Properties and Waysides Program directed a project to remove diseased trees and invasive species, and preserved the intact 1930s lilac hedge.

July, 2021 | A demonstration project with Northern Bedrock Historic Conservation Corps reconstructed one full table and pad in rock garden, using salvaged stone pieces stored in the Robbinsdale Public Works Yard. Included work on two picnic table pads in picnic area and some repointing on the overlook wall. Advanced Masonry Inc. was the Masonry Technical Expert.

May 1, 2023 | The St. Louis Park City Council voted to save historic Rock Island Park. A Say YES! to Rock Island Park Virtual Rally urged the city to save it from development. The north meadow parcel was purchased for $186,000.

June 30, 2023 | MnDot’s Historic Roadside Property Program completed their $500,000 project to preserve and restore Graeser Park. They restored the rare 1940 beehive fireplace, rebuilt 11 picnic tables, added accessible walks and repointied the rock garden pond walls and benches.

January 22, 2024 | After reviewing documentation from MnDOT, the Minnesota State Historic Preservation Office (SHPO) agreed that Graeser Park is eligible for listing in the National Register of Historic Places (NRHP).

December 23, 2025 | Thanks to MnDOT, dedicated volunteers, and a passionate community, Graeser Park was officially added to the National Park Service’s National Register of Historic Places.